---
date: "2007-03-14"
title: "Council Meeting Minutes 2007-03-14"
source: "2007-03-14-minutes-council-monthly.pdf"
---

CITY COUNCIL MEETING

March 14, 2007

Attended:

Stan Horrell, Mayor
Frank Primozic, Councilor
Tom McAuslan, Councilor
Bill Harrington, Councilor
Pam Woodworth, Councilor
Don Strong, Councilor
Jim Wood, Police Department
Bob Titus, Public Works
Brad Baird
Dean Hicks
Mona Lindsey

Mayor Horrell called the meeting to order at 6:00 p.m.  Roll call was called, Roger McKinley
being absent.  The pledge of allegiance was recited.  The minutes of the February 28, 2007
meeting were considered   MSP:  To approve the February 28 minutes as written, Tom
McAuslan, Frank Primozic.

The Council recognized Brad Baird of Anderson Perry & Associates.  Baird asked the City how
they would like to proceed with the completion of the water project.  It was generally recognized
that the City still has a contract with Anderson Perry but has been proceeding with the project
utilizing another engineer.  Baird gave the Council some background on the project and said they
had provided a water master plan to the City in the late 90’s.  Improvements identified were the
need for sand filtration to treat the water from the galleries and at least one additional well to
augment the supply.  The City sent out a request for proposals and chose Anderson Perry based
on qualifications.  After paying for the design and beginning advertisement for construction of
the sand filtration project, the City decided to actively pursue well drilling as an alternative and
put the sand filtration project on hold.  There was major concern at that point from both the
regulatory and funding agencies.  Since the contract provided for Sisul Engineering to sub-
contract with Anderson Perry to provide the well drilling portion of the project, that is who they
worked with.  For whatever reason, the two firms did not work out a sub-contract relationship.
There was discussion of the contract and Baird said Anderson Perry was to do the sand filtration
portion.  Sisul was to do the well drilling and design the pipeline and Anderson Perry is
responsible for designing the pump station.  Now that the well drilling has been completed, Baird
asked the Council which engineer they would like to continue with.  He said that even though
there is a contract, Anderson Perry does not want to make the City do something they don’t want
to do.  He was asked if Anderson Perry is still interested in the project.  He stated they are, but
because the City opted to pursue well drilling in lieu of installing the sand filtration system,
Anderson Perry has been completely removed from the loop and does not have any information
to move forward with.  There was speculation as to why the City proceeded without contacting
Anderson Perry throughout the project and it was noted that the City Recorder had reminded the

Minutes March 14, 2007

prior Council a number of times that Anderson Perry was still a part of it.  Baird cited the 30
years experience Anderson Perry has to offer and the added advantage of working with
contractors who have a certain comfort level when bidding their work that equates to lower costs.
There was also discussion of the potential problems with the funding agency due to not doing the
project in a timely manner.  The Recorder said the City’s contract with OECDD expired at the
end of December and has not been amended.  She said that Gary Viedorfer of OECDD has
indicated that the City has materially changed the scope of the project and may have to re-apply
for funding which would significantly affect the timeline in completing it.  By not honoring the
existing contact with Anderson Perry, the City would most likely be required to re-advertise and
re-award the project, causing further delays and sending red flags to the funding agency and the
Department of Human Services (Health Department.)  With regard to the contract, Baird said the
City could get out of it if they really want, but that Anderson Perry would require a release of
responsibility from that point forward.  Also, certain conditions regarding the designed sand
filtration system would need to be met in the case the City eventually pursued it.

There was discussion of the wells that have been drilled.  Bob Titus said they are good wells but
are not cased and that one had caved in.  Baird said Anderson Perry does not design wells as
open uncased holes because of the potential for cave in.  He noted concerns in taking over the
project because of the small size of the holes drilled and the lack of casing.  The City may have
saved some money by not casing them, but due to the small size of the holes the amount of water
drawn will be limited.  It was noted that the proposed landowner agreement limits the amount of
water the city can take to 400 gpm.  Tom McAuslan said it was news to him and others stated
they were also not aware of the restriction.  Baird also expressed concern that the City went
ahead with well drilling before they had a landowner contract in place.  It was also noted that
access agreements have not yet been secured either.  Baird said he would need to be brought up
to speed on the condition of the wells and the status of the agreements.  There was also
discussion of the million gallon reservoir and that it should be circulating water (state regulation)
to keep it from getting stagnant.  Bob Titus said they have been achieving that by dumping water
out of the overflow.  Baird said Anderson Perry has a plan to fix the circulation problem without
wasting the water by dumping it onto the ground.

There was general discussion of the City’s responsibility to honor the contract and the continued
delays in getting the project completed.  MSP:  To continue with the existing contract with
Anderson Perry, exempting the portion already completed by Sisul Engineering with a
release of responsibility, Bill Harrington/Pam Woodworth.

In moving forward, it was determined that the first step will be to get the funding agency on
board with the City’s plans and look at the remaining budget.  Anderson Perry will get together
with Sisul Engineering to establish a sub-contract relationship.  The City must work out the
property issues and get the landowner and access agreements finalized immediately in order to
get the project completed by this fall.  The City will need to consider casing the wells.  It was
agreed that Baird would communicate directly with the City Recorder with information intended
for the Council.

The Council recognized Assistant Fire Chief Dean Hicks who addressed them regarding the
placement of a water tank.  He explained that the Fire Department is required to pump test the

Minutes March 14, 2007

trucks and in order to do so must have access to water at ground level.  He said Prairie Wood
Products has donated an 11,000 gallon tank to the department and asked the Council for
permission to locate the tank on the industrial property.  He also asked the Council to consider
allowing the fire department to locate a fire training facility on the property.  He said the building
requires 1 acre and .2 acre for the drafting site and would be financed through grant funding.
The facility would be built on the northern portion of the property leaving plenty of room for
other development on the site.  The training facility would be utilized by other fire departments
and also available to law enforcement and ambulance for live situation training.  Hicks stated
that the City Recorder had agreed to help with the grant process.  There was discussion of the
advantages having the facility and if it should be reviewed by the Planning Commission.
MSP:  To approve the placement of the water tank subject to review by the Planning
Commission, Bill Harrington/Frank Primozic.  MSP:  To approve placement of the fire
training structure subject to review by the Planning Commission, Bill Harrington/Frank
Primozic.

Planning:  no report

Public Safety:  Jim Wood recapped the fire and police log activity and said things had been
fairly quiet.

Landfill:  Bob Titus turned in two written landfill reports.  He suggested Clark’s haul solid
waste to John Day in his absence (see below,) however, it was noted that the City loses revenue
whenever that occurs.  It was agreed the public works crew would be available to allow Clark’s
access to the site.  He also said that Marvin Rynearson had requested to dump ash and debris
(from a burned out house) in the landfill.  It was agreed that Titus should check the City’s permit
and with the DEQ to see if it is allowed.  If so, Rynearson will need to be advised he must weigh
the loads and provide a weight slip.  He will be charged $50 per ton to dispose of it.

Public Works:  Bob Titus gave the Council a written report and stated he would not be at the
next two meetings because he was taking some vacation time, returning April 9.  He said the
City of John Day had performed backflow tests and found a few problems.  It was noted that it is
up to the affected business to have a plumber make the repairs.  There was some discussion over
the cost of gear lube.

Well Drilling:  Mayor Horrell said he and Roger McKinley had met with John Coombs
regarding the landowner agreement and that Coombs was sending another draft to his attorney.

Other Business:  Mayor Horrell said that he, Officer Wood and the City Recorder had met with
the City’s insurance risk management representative and two people from Public Safety Liability
Management, Inc. to analyze the City’s current police services.  He said the interviews were very
comprehensive and hopes to receive a report from them in the next few weeks.

Bill Harrington reminded the Council that they had committed to making a decision regarding
the funding of the county’s Economic Development position by the end of March and asked to
have it put on the next agenda.

Minutes March 14, 2007

The City Recorder informed the Council that Judge Webb had contacted her and asked to
schedule a public meeting in Prairie City on Wednesday, March 21.  The meeting is to address
the proposed vacation of 13th Street between Strawberry Road and Hall Street and will be held at
6:00 p.m. at the Strawberry Grange.

Bill Harrington asked if the Council was going to consider hiring professional services to pack
and move the museum contents during the building renovation.  It was suggested that it would be
a good time to take an inventory and establish values for ownership and insurance purposes.
Frank Primozic was asked if he would be the main contact for museum matters, but he declined
due to time constraints.  He will still be involved, but noted that an additional person is needed.
The City Recorder volunteered to make contact with the Kam Wa Chung Museum in John Day
to see who they used to pack and move their items.  It was noted that containers will also be
needed.

8:15 p.m.  It was moved and seconded to adjourn the meeting.

Respectfully submitted:

___________________________
Diane Clingman, City Recorder

Approved this Date: ________________

_________________________________
Stan Horrell, Mayor

Minutes March 14, 2007

