Mayor Bradford called the special meeting to order, the pledge of allegiance was recited and the roll was called.

**Bids and Budget Overview:**

* Bids received (3 of 8 plan holders):
  + Hueckman Contracting LLC (low bidder)
  + Lovisone Construction
  + 3D Excavation and Construction
* Project structure:
  + Schedule A (Small City Allotment scope): ~$209,000 (within $250,000 ODOT grant)
  + Schedule B (City Hall improvements): ~$49,959 (city-funded; not grant-eligible)
* City budgets discussed:
  + Small City Allotment grant: $250,000
  + City Hall improvements budget: reduced to ~ $106,000 (prior discussion mentioned $100–120k range)

**Grant Scope and Potential Amendment**

* Current grant scope allows AC patching; chip seal originally contemplated.
* ODOT confirmed an amendment can be submitted to fully utilize the $250,000 by adding similar work (e.g., additional paving, ADA ramps).
* Preference expressed to defer chip seal to a county partnership program (more cost-effective: county provides equipment/labor; city pays oil/rock) and use current grant for asphalt patches and ADA ramps.

**City Hall Improvements (Schedule B)**

* Consensus: Proceed due to safety and deterioration concerns.
* Scope highlights:
  + Maintain existing south ramp and stairs.
  + Add new ADA ramp on north side wrapping east to van-accessible handicap parking.
  + Handicap parking added on north side; no impact to adjacent fire department access (generator/power).
  + Water meter/valve to be adjusted to grade; access maintained.
* Snowmelt/heated concrete discussion:
  + 5 bids received (electric systems), estimated $4,000–$10,000.
  + Life expectancy unknown; to be researched further.

**Use of Remaining Grant Funds (~$40,000)**

* Priorities discussed:
  + Complete all critical asphalt patches, especially:
    - Main Street (RWB/frontage; Water Alley)
    - McCallum/12th (water line trench area)
    - Other water repair patches (e.g., Johnson, near Dusty Williams/Carol Purvis)
  + Add ADA ramps for accessibility:
    - Focus on 5th & Main intersection (near post office and businesses), two ramps prioritized.
    - Consider additional ramps where feasible (e.g., 6th & Main), recognizing lack of sidewalk in some locations.
  + Prepare roads for future chip seal (crack sealing where appropriate, especially Bridge Street to align with county corridor).
    - Crack sealing cost rough order: ~$1/linear foot.
    - Each ADA ramp: ~ $5,000.
* **Engineer guidance:**
  + Chip seal best on roads in fair condition; not effective for alligatored roads.
  + Asphalt: ~$200/ton; $40k ≈ 200 tons (unit price basis in contract).
  + Consider ADA ramp packages at select intersections to improve town-wide ADA compliance incrementally.
  + Potential to use city crews for prep to stretch funds; contractor to pave under unit prices.
  + Striping needs to be included where ramps alter crossings.

**County Partnership for Future Chip Seal**

* County program (annual; application-based) likely provides:
  + Equipment/labor; city pays materials (oil/rock).
  + Past examples included county offering rock and crack sealing support.
* Strategic target: Bridge Street to extend existing county chip seal corridor through town, improving grant competitiveness.

**Decisions and Motions**

* Motion approved (unanimous):
  + Award contract to Heckman Contracting LLC as low bidder for:
    - Schedule A (grant-funded) and Schedule B (city-funded).
  + Contingent on no written bid protest within 7 days of Notice of Intent to Award.
  + Authorize Mayor Bradford(with Mayor McClung, Pro Tem as backup) to:
    - Sign Notice of Intent to Award, Notice of Award, contract documents, and Notice to Proceed.
    - Approve change orders up to $10,000 each to address unforeseen conditions (e.g., buried obstructions), with effort to notify Council if over $5,000.

**MSP: Councilor Ed Clark/McClung. Passed Unanimously**

* Direction to Staff:
  + Public Works (Mike, Brian) to provide by Friday:
    - A prioritized list beyond the 5th & Main ADA ramps, including:
      * Additional ADA ramps (e.g., 6th & Main if feasible).
      * Asphalt patches (all critical water-line trench patches, key intersections).
      * Crack sealing candidates (prepare Bridge Street for future chip seal).
  + Engineer (Joe) to:
    - Use unit bid prices to price the added items.
    - Prepare ODOT amendment request to reallocate from chip seal to the selected like-for-like improvements.
  + Proceed to issue Notice of Intent to Award immediately; after 7 days without protest, issue Notice of Award and contracts.

**Next Steps and Timeline**

* Immediate:
  + Mayor to sign Notice of Intent to Award; distribute to bidders.
  + Public Works submits prioritized list by Friday.
  + Engineer compiles amendment package for ODOT with final list.
* Short-term:
  + 7-day protest period concludes; issue Notice of Award and contracts.
  + Target start of construction in early fall; work likely continues into October.
* Ongoing:
  + Explore county chip seal application when program opens.

**Adjournment**

* MSP: To adjourn the meeting. Councilor Coburn/Clark. Approved unanimously.
* Meeting adjourned.

Approved by the City Council on this 14th day of October 2026 and signed by the Mayor.